Option to view the planned start date and end date through the viewer in eclipse


Bharath Adhithya (5213352) | asked Dec 03 '13, 3:54 a.m.
RTC does not provide option to view the planned start date and end date through the viewer in eclipse. How can this be viewed in eclipse viewer?

Comments
Aradhya K commented Dec 03 '13, 4:21 a.m.
JAZZ DEVELOPER

In Eclipse which editor are you interested in?

Work item Editor or Plan Editor.


Bharath Adhithya commented Dec 03 '13, 4:27 a.m.

In Plan editor

One answer



permanent link
Ralph Schoon (63.7k33648) | answered Dec 04 '13, 5:42 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
As far as I know, this is not available in the Eclipse client. There is a big push from users to use the web client as much as possible. It is hard and error prone to develop everything twice, I guess. So new features like formal planning, Gantt charts, road maps are only implemented in the web UI. The Eclipse Planning client stays to be capable of working, but many of the new features are unfortunately not available.

If you try to configure a plan view in Eclipse (formal project management) you realize that the planned start date pseudo attribute is not even available for choice. This value is only available by a calculation done in the formal scheduler and the attribute you choose is really only a calculated value and does not surface as real attribute anywhere, 