Missing triangle to indicate current iteration.
I have two projects on the same Jazz instance. When setting the "Planned For" field on a Work Item, the one that uses the Eclipse Way Process will display a triangle for the current iteration but the one using the Scrum process won't
I've tried comparing the projects to various others but I've run out of ideas. Does anyone know what I need to do to get the current iteration triangle to display?
Thanks.
I've tried comparing the projects to various others but I've run out of ideas. Does anyone know what I need to do to get the current iteration triangle to display?
Thanks.
One answer
Hi Andrew,
You are using the eclipse client? The current iteration triangle only shows up for the current iteration of the project timeline - is the iteration in the Scrum project not under the project timeline?
You are using the eclipse client? The current iteration triangle only shows up for the current iteration of the project timeline - is the iteration in the Scrum project not under the project timeline?
Comments
Hi Parker,
Sorry for the delayed reply. I posted this query and then went on holiday for a week.
I'm using the web client.
If I look in Manage Project -> Timelines for the scrum project I can see several timelines, including Main Development, that have a current iteration but none of these will show with an arrow by its side. In the other project, the current iteration of the Main Development timeline shows with an arrow by its side.