Relationship of work items
Assume that a "story" work item has a number of child "task" work items.
The estimated hours for the task work items total more than the parent story estimate. Is there any way that the user can be warned of this? The "story" is moved into a later iteration. The child tasks are not moved. Is there any way that the children can be moved, too? |
One answer
Hi Pat,
the estimate on the story should only be used if with the story itself work is assigned. Otherwise it is not necessary since the progress and load bars do the roll up of the estimates automatically. Select the children as well in the plan (the ones you want to move) and execute Plan For from the context menu. Dirk Bumer Agile Planning Component PatSilva wrote: Assume that a "story" work item has a number of child |