It's all about the answers!

Ask a question

Regarding importing existing MS project plan into RTC


Monika Gupta (15279) | asked Aug 07 '13, 8:11 a.m.

I have a requirement where I need to upload an already running project's data/progress into RTC. Please tell me how to address this requirement.

also  I need to know if I can set the start date of the tasks to the date in past while taking snapshot or importing the project plan.

Please provide inputs if anyone came across such a situation and how they handled it.

Thanks

One answer



permanent link
Stephanie Bagot (2.1k1513) | answered Aug 08 '13, 11:51 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
We do support importing MS project plans into RTC. See the following Information Center article for information on completing this task:
http://pic.dhe.ibm.com/infocenter/clmhelp/v4r0m1/index.jsp?topic=%2Fcom.ibm.team.apt.doc%2Ftopics%2Fc_import_and_export_projects.html

Comments
Monika Gupta commented Aug 09 '13, 5:40 a.m.

 I know this and have been using this feature. My requirement is to upload an already running project's progress/data. If I upload the plan, it calculates the planned start etc. from the day I take snap shot, I want to give the start date as the date in past. 


Please let me know how this can be done? I tried applying some constraints as well, but still planned dates are with respect to the current date. 

Your answer


Register or to post your answer.