JazzHub Beta 3 - Can't change Effort Tracking unit in taskboard view

 I have tasks wit estimated effort. I want to change the estimate from the Taskboard.
Instead of using the drop down list to set a new value, I want to change my estimate from 5 h to 5 d.
I can't expand the unit drop down list box

Task

0 votes


Accepted answer

Permanent link
Thanks for letting us know!  I've reproduced the issue and will file a defect.
JL Marechaux selected this answer as the correct answer

0 votes


One other answer

Permanent link
I have a similar issue, but different: I can't change and save the effort on a taskboard to a higher value than the current estimate. I can change it, but I can't save it and the error message does not tell me which work item is flawed.

For example, with a current estimate is 8 hours, I can fill in 3 hours (i.e. estimate remains 8 hours but remaining becomes 3 hours), but I cannot fill in and save 10 hours. To achieve that I need to open the work item, fill in correction of (at least) 10 hours and fill in remaining 10 hours.

What is the work item ID corresponding to this issue?

0 votes

Comments

Hi Frank,
The defect for the issue initially reported in this question is tracked at Unable to change estimate units in taskboard view (268060).

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220
× 383

Question asked: Jun 05 '13, 10:24 p.m.

Question was seen: 4,955 times

Last updated: Apr 04 '14, 11:58 a.m.

Confirmation Cancel Confirm