I am using RTC 3.0, AF plugin is 3.4.2. After customization and open the plan, bellow error occured:

Planning can not be used because the Project Configuration is invalid. Check the details for further information.: Unable to resolve the planning attribute 'com.ibm.team.apt.attribute.planitem.constraintDate' as work item attribute 'com.ibm.team.apt.attribute.constraintdate'.

One answer



permanent link
Ralph Schoon (63.6k33646) | answered Mar 04 '13, 3:56 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi, I am not sure what kind of customization you have been doing and where, but the plan tries to find an attribute that is configured in the Plan Attributes or another section in the Planning area of the Process Configuration>Configuration Data. Looking a the ID's the interesting observation is that one ID is com.ibm.team.apt.attribute.planitem.constraintDate and another is com.ibm.team.apt.attribute.constraintdate. I am not sure why, but one has a capital D, where the other has a lower case d.

You need to fix what you did otherwise your plan won't load. Also see https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/230709 . The work item is around enhancing RTC to be more resilient in case of configuration issues with planning.