Calculation of Proposed/Planned start and end date in plan


mahalakshmi V (0168) | asked Feb 18 '13, 9:12 a.m.
How does the proposed/planned start and end date gets calculated in plan of RTC 4x?

One answer



permanent link
Ralph Schoon (62.7k33643) | answered Feb 19 '13, 3:23 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
That depends on the process template. Please consider looking at these articles: https://jazz.net/library/#tag=planning

Especially https://jazz.net/library/article/658 and https://jazz.net/library/article/657 and https://jazz.net/library/article/761

To my knowledge the
  • Agile scheduler determines the order based on priority/rank/ownership/allocation/availability/estimate
  • Formal scheduler determines the order based on dependencies, allocation, availability, estimate and dependencies

Based on the order the planned start/end times are calculated.