Calculation of Proposed/Planned start and end date in plan
One answer
That depends on the process template. Please consider looking at these articles: https://jazz.net/library/#tag=planning
Especially https://jazz.net/library/article/658 and https://jazz.net/library/article/657 and https://jazz.net/library/article/761
To my knowledge the
Especially https://jazz.net/library/article/658 and https://jazz.net/library/article/657 and https://jazz.net/library/article/761
To my knowledge the
- Agile scheduler determines the order based on priority/rank/ownership/allocation/availability/estimate
- Formal scheduler determines the order based on dependencies, allocation, availability, estimate and dependencies
Based on the order the planned start/end times are calculated.