Planned For dropdown in work items are not showing all iterations
I want to better organize the work items within a project so I created some new iterations and associated plans. However when I go to an existing work item to try to assign it to one of the new iterations, I don't see them in the Planned For dropdown. Added these iterations last week and they still are not showing. Using 4.0 and the web browser.
|
Accepted answer
Are these iterations added to the timeline that is set as current timeline?
Best Regards
Tina Zeman selected this answer as the correct answer
|