Hi

RQM 4.0

To make the reviewer to be added mandatory before changing the state to ready for review for a test case, I have a added rule at the RTC Eclipse client, (Infact tried adding all the 11 Preconditions).
Unfortunately, In RQM, I am still able to save the test case  without adding the reviewer / approver ?



Any Inputs on how do I achieve this?

Regards
Rajesh

One answer



permanent link
Pramod Chandoria (2.1k11220) | answered Sep 14 '12, 12:34 p.m.
JAZZ DEVELOPER
Hi Rajesh
Do you mean you tried this advisor "Disallow transition to Approved until All approvers approve"
for Test plan?

Comments
Rajesh Avanthi commented Sep 14 '12, 1:08 p.m.

Hi Pramod

Yes, this particular advisor was selected in RTC client. Even though selected, the user can create and save the testcase without the approvers being assigned and approved.


Pramod Chandoria commented Sep 14 '12, 1:23 p.m.