Can I have multiple release for one sprint?
Hello,
Is it possible to have multiple releases targeting the same sprint in RTC 3.0.x?
Thanks in advance
|
2 answers
A release contains sprints..
when we do this we have parallel timelines/releases/sprints (with the same time schedules) , so that you can have multiple releases of different stuff completed at the same time. (by the same or different teams).. the PLAN views are also parallel however. Sam |
Geoffrey Clemm (30.1k●3●30●35)
| answered Sep 01 '12, 7:03 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
It depends on what you mean by "multiple releases targeting the same sprint".
But assuming it means you have two releases of different products, you would just create two team areas (one for each release), and have the both team areas use the timeline in which that sprint is defined. |