There is any way in RTC to get the time tracking of each devolper working in workitem? or i need to implement a independent workitem to register like a weekly report ?
I know that in the planning configuration data there are option than mension things about time tracking but i dont know if this can be useful for what i need. CLM 2012 - 4.0 version |
2 answers
I don't believe that the time tracking information is written to the data warehouse by RTC. If it isn't, then the data isn't available to RRDI reports.
|
Work item "Time tracking tab" data are exposed for BIRT, so you can fetch timesheets and design almost any kind of such report. Another way maybe using Insight with customized ETLs, but Insight is commercial tool.
Comments
David Murphy
commented Jan 28 '13, 1:47 p.m.
Would you be willing to share a BIRT report template for this type of report so we wouldn't have to start from scratch? |