Robbie Minshall (143) | asked Sep 09 '08, 1:28 p.m.
JAZZ DEVELOPER
I have a high level task ( it is a story ), with many children ( these are tasks ) that get contained within an iteration.
It works well and I like the high level progress bar I can see on my high level story.

I use the burndown charts for each iteration and would like one for these high level story which spans iterations.

I would like to be able to create some reports on a high level stories progress ( burndown, or projected outlook ) ... how can I do this ?

Robbie

2 answers



permanent link
Dirk Baeumer (4811) | answered Sep 10 '08, 12:20 p.m.
JAZZ DEVELOPER
Burndown reports are not available for a single task. They are only
available for the work items contained in an iteration.

Please file a enhancement request for such reports against Reports in
teh Jazz.net repository

Dirk
Agile Planning team

rjminsha wrote:
I have a high level task ( it is a story ), with many children (
these are tasks ) that get contained within an iteration.
It works well and I like the high level progress bar I can see on my
high level story.

I use the burndown charts for each iteration and would like one for
these high level story which spans iterations.

I would like to be able to create some reports on a high level stories
progress ( burndown, or projected outlook ) ... how can I do this ?

Robbie

permanent link
James Moody (3.3k24) | answered Sep 10 '08, 2:03 p.m.
JAZZ DEVELOPER
Robbie and I had an offline chat about this, and for anyone who's
interested we'll track this work in:

https://jazz.net/jazz/web/projects/Jazz%20Project#action=com.ibm.team.workitem.viewWorkItem&id=60822

james
Jazz Reports Team Lead

Dirk Bumer wrote:
Burndown reports are not available for a single task. They are only
available for the work items contained in an iteration.

Please file a enhancement request for such reports against Reports in
teh Jazz.net repository

Dirk
Agile Planning team

rjminsha wrote:
I have a high level task ( it is a story ), with many children (
these are tasks ) that get contained within an iteration. It works
well and I like the high level progress bar I can see on my
high level story.
I use the burndown charts for each iteration and would like one for
these high level story which spans iterations.

I would like to be able to create some reports on a high level stories
progress ( burndown, or projected outlook ) ... how can I do this ?

Robbie

Your answer