How is a "Requirements Change Request" supposed to be initiated?

I can see lots of configuration info in our Project Area for "Requirements CR" etc, with "Uses" and "Provides" links,  "Change Management Type Binding" defined.

I have not yet seen how a user is expected to initiate a change request against a requirement. Can anyone give examples?

0 votes


Accepted answer

Permanent link
One usage is to create a change request work item, and then use the Tracked By link to the requirement
Andrew Codrington selected this answer as the correct answer

1 vote

Comments

Thank you! That's helpful.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,023

Question asked: Jul 12 '12, 5:44 p.m.

Question was seen: 5,103 times

Last updated: Jul 16 '12, 10:04 a.m.

Confirmation Cancel Confirm