how to create a sprint burndown for a team across multiple releases
If I have a project/product with multiple concurrent releases each with their own sprints and then have a team that may work on one sprint in one release and another sprint in another release, how can I create a sprint burndown on the work the team is working on that covers all the work they are working across the multiple releases. . |
One answer
Millard Ellingsworth (2.5k●1●24●31)
| answered Jul 11 '12, 2:53 p.m.
FORUM ADMINISTRATOR / JAZZ DEVELOPER
The Sprint Burndown report is configured against a Team Area which is associated with a timeline. From your description, it sounds like you have multiple timelines (releases) which means that this "team" is captured in two different team areas, one associated with each timeline. There is currently no way to aggregate them into a single burndown. There are similar issues with providing a single plan for such a team configuration as tracked by this Enhancment Request: https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=215125
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.