Using RTC 3.0.1.3, I want to track work items based on estimate attribute.
I found that Workitem Estimate has not Unassigned option in Web query but it exists in Eclipse client.
Is it a bug?

One answer



permanent link
Eric Jodet (6.3k5111120) | answered Jun 08 '12, 8:17 a.m.
JAZZ DEVELOPER
This issue is identified on jazz.net with enhancement # 157599
Support the "Unassigned" condition for timestamps in the Web UI (157599)