Hi All,

v.3.0.1 of RRC/RQM.

I created a few projects with all the 3 sub-projects (RRC, CCM and RQM). When I create a Requirement in RRC, I have the ability to link it to requirements in other projects of RRC, however, when I want to add requirements to a Test Case in QM, QM is only letting me view requirements for the RM project with the same name as the QM project. I thought that with RRC being able to link across projects, QM would also have the same functionality.

Is it possible to link a Test Case in Project A with a Requirement in Project B? If so, how?

Thanks,

0 votes



One answer

Permanent link
Never mind! It was as simple as adding the associations to other projects in the Manage This Project Area section!

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: May 15 '12, 12:39 p.m.

Question was seen: 6,496 times

Last updated: May 15 '12, 12:39 p.m.

Confirmation Cancel Confirm