Displaying estimate time
Hello.
We have problem with displaying estimate time for tasks.
We changed our work hours per day from 8 hours to 5 hours.
In the task view panel the field "Estimate" seems correct. (If we defined 20 hours for task its shows 4d).But in the Plan view panel it's seems incorrect, its shows 2d 4h.
May be someone know how to fix it?
Thanks for help.
We have problem with displaying estimate time for tasks.
We changed our work hours per day from 8 hours to 5 hours.
In the task view panel the field "Estimate" seems correct. (If we defined 20 hours for task its shows 4d).But in the Plan view panel it's seems incorrect, its shows 2d 4h.
May be someone know how to fix it?
Thanks for help.
3 answers
I've opened defect 59774 to track this.
Christof
Jazz Work Item team
sergeyf wrote:
Christof
Jazz Work Item team
sergeyf wrote:
Hello.
We have problem with displaying estimate time for tasks.
We changed our work hours per day from 8 hours to 5 hours.
In the task view panel the field "Estimate" seems correct.
(If we defined 20 hours for task its shows 4d).But in the Plan view
panel it's seems incorrect, its shows 2d 4h.
May be someone know how to fix it?
Thanks for help.
The planned items view in the iteration plan editor translates the enter
estimates into project time to enusre that 1d for owner a means the same
as 1d for owner be even if both users have specified a different work
time per day. Otherwise the values would not be comparable to each
other. You can configure the project time in the Process spec. Go to
Process Configuration > Project Configuration > Configuration Data >
Iteration Plans > Work Environment.
Dirk
Agile Planning team
sergeyf wrote:
estimates into project time to enusre that 1d for owner a means the same
as 1d for owner be even if both users have specified a different work
time per day. Otherwise the values would not be comparable to each
other. You can configure the project time in the Process spec. Go to
Process Configuration > Project Configuration > Configuration Data >
Iteration Plans > Work Environment.
Dirk
Agile Planning team
sergeyf wrote:
Hello.
We have problem with displaying estimate time for tasks.
We changed our work hours per day from 8 hours to 5 hours.
In the task view panel the field "Estimate" seems correct.
(If we defined 20 hours for task its shows 4d).But in the Plan view
panel it's seems incorrect, its shows 2d 4h.
May be someone know how to fix it?
Thanks for help.
Hello.
We have problem with displaying estimate time for tasks.
We changed our work hours per day from 8 hours to 5 hours.
In the task view panel the field "Estimate" seems correct. (If we defined 20 hours for task its shows 4d).But in the Plan view panel it's seems incorrect, its shows 2d 4h.
May be someone know how to fix it?
Thanks for help.
Yes - i've seen something similar myself.
With a 5 hour day defined for the project (and myself) i create a workitem with estimate of 10 hours.
When I save it and look at it in the webUI it shows as 1day 2hours, but if i use the RTC client and view it, it shows as "2d"