Main development iterations - overlapping timelines?
One answer
Yes, currently, there is no checking done to prevent iterations from overlapping in dates. I personally would find that situation confusing at best, so I would never do it myself.
Cheers,
Geoff
Cheers,
Geoff
Can I have iterations under Main Development that are overlapping in dates?
Main Development (project timeline)
I1 4/24/12 - 5/24/12
I2 5/15/12 - 6/24/12
I3 6/01/12 - 8/25/12
What are the implications of having overlapping dates?