Why do product backlogs have to be within a sprint?
I'm evaluating RTC at the moment (i.e. a n00b), and some of it is a little confusing.
So I need to create a product backlog, which in the Scrum universe is its own artefact, separate from any sprint or iteration. In RTC, I create a new plan and configure it to be a Product Backlog. It automatically assigns it to a Sprint that I'd previously configured (Sprint 0). Why do Product backlogs have to be in an iteration/sprint in RTC? Is there any way to have the Product Backlog and Release Backlog separate from any sprint? Cheers, R |
4 answers
Geoffrey Clemm (30.1k●3●30●35)
| answered Oct 27 '11, 12:55 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Product backlogs are represented as an iteration in RTC because an
iteration lets you do all the things that you normally want to do with a backlog. Logically, a backlog is the "catchall" iteration, for all the things that aren't assigned to another iteration. Note: In version one, RTC had a separate concept of a backlog, but we kept getting requests to be able to do additional things to the backlog, and those things were already supported on iterations. So in later releases, we just made the backlog be an iteration, and marked all those enhancement requests as "Done". Cheers, Geoff On 10/27/2011 9:38 AM, rlissimore wrote: I'm evaluating RTC at the moment (i.e. a n00b), and some of it is a |
I'd argue the difference between a list of work to do (backlog) and a period of time (iteration), but it won't change how it works.
Are there any other quirks like this in RTC? Anything that isn't straightforward? Product backlogs are represented as an iteration in RTC because an I'm evaluating RTC at the moment (i.e. a n00b), and some of it is a |
Geoffrey Clemm (30.1k●3●30●35)
| answered Oct 28 '11, 1:36 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
If the question is "Is there anything else I personally will find
non-intuitive", then the answer almost certainly will be "yes". Probably the best way to find things that others have found non-intuitive would be to browse this forum. Cheers, Geoff On 10/28/2011 9:23 AM, rlissimore wrote: I'd argue the difference between a list of work to do (backlog) and a |
I would not think to much why a backlog is represented in RTC as an Iteration. It must be something and the Object Iteration has the functionality you need to build a Backlog.
A Backlog must not be in a Sprint. I have it parallel to a Sprint. My favorite setup is
Release
Sprint 1 Sprint 2 Sprint 3 This allows me to create following plans: - Product Backlog > uncommitted (Type Product Backlog) - Release Plan > Release (Type Release Backlog) - Release Backlog > Backlog (Plan Type Product Backlog) - Sprint Plan > Sprint x (Plan Type Sprint Backlog) (Note: If you use Plan type Release Backlog for the Release Backlog, at least the Advanced Burndown Chart report will not work, because there it is not allowed to select two Iterations where a Release Backlog Plan exists.) What I absolutly dont like, and it confuse the users, is the word Backlog in the plan types. But its just a word. regards Guido |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.