about caculation of the remaining iteration working hours
User Bill's work environment is five days(monday to friday),8 hours(quitting time is 5:00pm)
Iteration X's schedule is from 20/6 to 7/7(monday)
Bill is fully dedicated(100%) to iteration X
Now at 10:00pm 4/7(friday),the X's iteration plan->work items view shows that Bill still has 16 hours working time,for saturday and sunday are excluded, RTC regards the current working day(7/4 friday) as 8 hours working time even there is only 2 hours left, actually all working time of this current day has been used up(attention: quitting time is 5:00pm)
When the day is saturday(5/7),RTC works well and iteration plan->work items view shows that Bill has 8 hours working time left(7/7 monday)
Can anyone give a detailed explanation about the mechanism of caculation of the remaining iteration working hours? and i want to know how RTC determines the current date/time, by RTC server OS's date/time? or anything else?
Thanks a lot!
Iteration X's schedule is from 20/6 to 7/7(monday)
Bill is fully dedicated(100%) to iteration X
Now at 10:00pm 4/7(friday),the X's iteration plan->work items view shows that Bill still has 16 hours working time,for saturday and sunday are excluded, RTC regards the current working day(7/4 friday) as 8 hours working time even there is only 2 hours left, actually all working time of this current day has been used up(attention: quitting time is 5:00pm)
When the day is saturday(5/7),RTC works well and iteration plan->work items view shows that Bill has 8 hours working time left(7/7 monday)
Can anyone give a detailed explanation about the mechanism of caculation of the remaining iteration working hours? and i want to know how RTC determines the current date/time, by RTC server OS's date/time? or anything else?
Thanks a lot!
5 answers
lilo wrote:
You provided the answer yourself already. We don't consider the current
time, but the day only. Feel free to file an enhancement.
--
Cheers, Johannes
Agile Planning Team
User Bill's work environment is five days(monday to friday),8
hours(quitting time is 5:00pm)
Iteration X's schedule is from 20/6 to 7/7(monday)
Bill is fully dedicated(100%) to iteration X
Now at 10:00pm 4/7(friday),the X's iteration plan->work items view
shows that Bill still has 16 hours working time,for saturday and
sunday are excluded, RTC regards the current working day(7/4 friday)
as 8 hours working time even there is only 2 hours left, actually all
working time of this current day has been used up(attention: quitting
time is 5:00pm)
When the day is saturday(5/7),RTC works well and iteration
plan->work items view shows that Bill has 8 hours working time
left(7/7 monday)
You provided the answer yourself already. We don't consider the current
time, but the day only. Feel free to file an enhancement.
--
Cheers, Johannes
Agile Planning Team
:roll: :roll: :roll: :roll: :roll: :roll:
is there any expert gives me a hand? please, it's so bad to get no response from a open forum,no to say that some of you are RTC designers.
Hi - you have asked your question on Friday. Since we just have shipped RTC 1.0 the team has a well deserved free Friday during July. We do our best to be responsive so please continue asking questions.
--erich gamma
Jazz PMC Lead
:roll: :roll: :roll: :roll: :roll: :roll:
is there any expert gives me a hand? please, it's so bad to get no response from a open forum,no to say that some of you are RTC designers.
Hi - you have asked your question on Friday. Since we just have shipped RTC 1.0 the team has a well deserved free Friday during July. We do our best to be responsive so please continue asking questions.
--erich gamma
Jazz PMC Lead
Thanks egamma, I have submitted a RFE(https://jazz.net/jazz/web/projects/Jazz%20Project#action=com.ibm.team.workitem.viewWorkItem&id=58877)