Matthias Schippmann (634) | asked Sep 15 '11, 9:15 a.m.
Hi,

is there any possibility to copy a complete RQM project from one server to another?

Background: We want to copy an existing project area into a training environment for several times over the year.

Thanks in advance for any suggestions!

Matthias

One answer



permanent link
Paul Slauenwhite (8.4k12) | answered Sep 16 '11, 7:43 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
Unfortunately, no. See:

https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/170097
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/139931
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/101257

You can copy all of the RQM resources from one project area/repository to another (same RQM version) using the RQM Copy Utility (see https://jazz.net/wiki/bin/view/Main/RQMCopyUtility).