Switch order of sub-iterations in Timeline?
Is there a way to switch the order of sub-iterations in the Timelines?
New Development I1 I2 . . . I9 I11 I10 I created our I11 sub-iteration before I10 like above and now that I10 is the Current Iteration it thinks that I11 is complete and has the icon with the checkmark next to it. It also isn't appearing in the Plan view as a Planned For option. I looked in the Eclipse Client on the Overview tab but didn't see anything obvious. Searching Help or the forums didn't bring anything back either. For now I made I11 the Current Iteration so it would appear but that isn't ideal. I'm using 3.0.1 |
One answer
Geoffrey Clemm (30.1k●3●30●35)
| answered Aug 18 '11, 11:45 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
In the Eclipse client, you can use the "move" operation (one of the tool
icons). If you "move" it under a parent, it will make it the last child of that parent. If you "move" it to a sibling, it will make it the immediate next child after that sibling. Cheers, Geoff On 8/18/2011 7:23 PM, miwalker wrote: Is there a way to switch the order of sub-iterations in the |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.