Tracking Story Points in Burn Downs?

Is it possible to configure RTC to track story points for burndowns (and capacity for that matter) rather than time?

Time is a pretty useless metric for agile burndowns and planning.

Thanks!

0 votes



One answer

Permanent link
Hi Trevor,

RTC does track complexity such as story points on top level work items. This is also fed in Burndown, Burnup etc. An example set up for this is the scrum process template. One article that might help you further can be found here: http://jazz.net/library/article/201.

Thanks,

Ralph

Is it possible to configure RTC to track story points for burndowns (and capacity for that matter) rather than time?

Time is a pretty useless metric for agile burndowns and planning.

Thanks!

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Feb 07 '11, 12:50 p.m.

Question was seen: 7,373 times

Last updated: Feb 07 '11, 12:50 p.m.

Confirmation Cancel Confirm