My Work view
In My Work view I can right click on an item and select Show Work Time to display:
Original Estimate
Corrected Estimate
Time Remaining
Yesterday when I selected Show Work Time it displayed:
Minimal
Nominal
Maximal
Time Remaining
It is only displaying this way for me, so I must have changed something by mistake. I haven't been able to find what controls this, and the help file has nothing on it.
Does anyone know where/how this is controlled?
Thanks
Original Estimate
Corrected Estimate
Time Remaining
Yesterday when I selected Show Work Time it displayed:
Minimal
Nominal
Maximal
Time Remaining
It is only displaying this way for me, so I must have changed something by mistake. I haven't been able to find what controls this, and the help file has nothing on it.
Does anyone know where/how this is controlled?
Thanks
2 answers
In My Work view I can right click on an item and select Show Work Time to display:
Original Estimate
Corrected Estimate
Time Remaining
Yesterday when I selected Show Work Time it displayed:
Minimal
Nominal
Maximal
Time Remaining
It is only displaying this way for me, so I must have changed something by mistake. I haven't been able to find what controls this, and the help file has nothing on it.
Does anyone know where/how this is controlled?
Thanks
There's a menu option for that view.
In the My Work view, click on menu -> Schedule risk assessment -> Uncheck 'Enable'.
That should bring it back to Estimates & Time Remaining.