Joseph Moore (61) | asked Sep 10 '10, 2:55 p.m.
In My Work view I can right click on an item and select Show Work Time to display:
Original Estimate
Corrected Estimate
Time Remaining

Yesterday when I selected Show Work Time it displayed:
Minimal
Nominal
Maximal
Time Remaining

It is only displaying this way for me, so I must have changed something by mistake. I haven't been able to find what controls this, and the help file has nothing on it.

Does anyone know where/how this is controlled?

Thanks

2 answers



permanent link
David Castellanos (20686) | answered Sep 10 '10, 3:16 p.m.
In My Work view I can right click on an item and select Show Work Time to display:
Original Estimate
Corrected Estimate
Time Remaining

Yesterday when I selected Show Work Time it displayed:
Minimal
Nominal
Maximal
Time Remaining

It is only displaying this way for me, so I must have changed something by mistake. I haven't been able to find what controls this, and the help file has nothing on it.

Does anyone know where/how this is controlled?

Thanks


There's a menu option for that view.
In the My Work view, click on menu -> Schedule risk assessment -> Uncheck 'Enable'.
That should bring it back to Estimates & Time Remaining.

permanent link
Joseph Moore (61) | answered Sep 10 '10, 3:22 p.m.


There's a menu option for that view.
In the My Work view, click on menu -> Schedule risk assessment -> Uncheck 'Enable'.
That should bring it back to Estimates & Time Remaining.