My Work view

In My Work view I can right click on an item and select Show Work Time to display:
Original Estimate
Corrected Estimate
Time Remaining

Yesterday when I selected Show Work Time it displayed:
Minimal
Nominal
Maximal
Time Remaining

It is only displaying this way for me, so I must have changed something by mistake. I haven't been able to find what controls this, and the help file has nothing on it.

Does anyone know where/how this is controlled?

Thanks

0 votes



2 answers

Permanent link
In My Work view I can right click on an item and select Show Work Time to display:
Original Estimate
Corrected Estimate
Time Remaining

Yesterday when I selected Show Work Time it displayed:
Minimal
Nominal
Maximal
Time Remaining

It is only displaying this way for me, so I must have changed something by mistake. I haven't been able to find what controls this, and the help file has nothing on it.

Does anyone know where/how this is controlled?

Thanks


There's a menu option for that view.
In the My Work view, click on menu -> Schedule risk assessment -> Uncheck 'Enable'.
That should bring it back to Estimates & Time Remaining.

0 votes


Permanent link


There's a menu option for that view.
In the My Work view, click on menu -> Schedule risk assessment -> Uncheck 'Enable'.
That should bring it back to Estimates & Time Remaining.


Thanks Dave, that did it.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Sep 10 '10, 2:55 p.m.

Question was seen: 5,220 times

Last updated: Sep 10 '10, 2:55 p.m.

Confirmation Cancel Confirm