Iteration plan limited to 3 levels deep in development line?
I have a development line based on OpenUP that in some places goes four levels deep, e.g. Main dev -> Construction -> Construction Iteration C1 -> Development. When I create an iteration plan, Development isn't an option as an iteration but those iterations above it are. Why is that the case?
One answer
I suspect you are using beta2. This limitation has been lifted in M5.
Kai
Jazz Process team
tfeeney wrote:
Kai
Jazz Process team
tfeeney wrote:
I have a development line based on OpenUP that in some places goes
four levels deep, e.g. Main dev -> Construction -> Construction
Iteration C1 -> Development. When I create an iteration plan,
Development isn't an option as an iteration but those iterations
above it are. Why is that the case?