Disable the creation of Initial work items


babu vijay prasad kamineni (7623016) | asked Jun 17 '10, 8:46 a.m.
Initially when i create a new project there are several work items which are created automatically. Is there any way of disabling those work items to be created?

2 answers



permanent link
Jean-Michel Lemieux (2.5k11) | answered Jun 20 '10, 11:36 p.m.
JAZZ DEVELOPER
Yes this is possible. The creation of the initial work items are performed by a project creation follow-up action. If you open the project area editor and switch to the "Process Configuration" page, then in the Configuration tree expand to the "Project Configuration > Project Area Initialization" you'll see in the right a server follow-up action called "Setup Project". This creates streams and work items. You can customize it or update the template you use so that new projects have a different initialization behavior.
Cheers,
Jean-Michel

permanent link
babu vijay prasad kamineni (7623016) | answered Jun 22 '10, 6:19 a.m.
Yes this is possible. The creation of the initial work items are performed by a project creation follow-up action. If you open the project area editor and switch to the "Process Configuration" page, then in the Configuration tree expand to the "Project Configuration > Project Area Initialization" you'll see in the right a server follow-up action called "Setup Project". This creates streams and work items. You can customize it or update the template you use so that new projects have a different initialization behavior.
Cheers,
Jean-Michel


Thank you very much Jean Michel. Your reply helped me a lot