It's all about the answers!

Ask a question

Disable the creation of Initial work items


babu vijay prasad kamineni (7623016) | asked Jun 17 '10, 8:46 a.m.
Initially when i create a new project there are several work items which are created automatically. Is there any way of disabling those work items to be created?

2 answers



permanent link
babu vijay prasad kamineni (7623016) | answered Jun 22 '10, 6:19 a.m.
Yes this is possible. The creation of the initial work items are performed by a project creation follow-up action. If you open the project area editor and switch to the "Process Configuration" page, then in the Configuration tree expand to the "Project Configuration > Project Area Initialization" you'll see in the right a server follow-up action called "Setup Project". This creates streams and work items. You can customize it or update the template you use so that new projects have a different initialization behavior.
Cheers,
Jean-Michel


Thank you very much Jean Michel. Your reply helped me a lot

permanent link
Jean-Michel Lemieux (2.5k11) | answered Jun 20 '10, 11:36 p.m.
JAZZ DEVELOPER
Yes this is possible. The creation of the initial work items are performed by a project creation follow-up action. If you open the project area editor and switch to the "Process Configuration" page, then in the Configuration tree expand to the "Project Configuration > Project Area Initialization" you'll see in the right a server follow-up action called "Setup Project". This creates streams and work items. You can customize it or update the template you use so that new projects have a different initialization behavior.
Cheers,
Jean-Michel

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.