RTC Project TimeLine
In Scrum process: The Release has been divided to several Sprint. If the release time line (start date 1st May 2010 , END date 31st june 2010) And the release has been divided to 2 sprint.
Sprint 1: 1st may to 31st may Sprint 2 : 1st june to 31th June which is correct. but now if i change the sprint2 time line which will be complete by 2nd july (> that end date of release 1.) RTC project Area should now allow me to save. Not sure whether its a right Approach to do or not. Ideally the sprint timeline should not be greater than release End date |
One answer
Geoffrey Clemm (30.1k●3●30●35)
| answered May 03 '10, 6:56 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
This functionality is currently requested in 88814. There is some
discussion in that work item as to whether it should just be a warning, or whether it should be an error. If you wish to indicate your support/interest in the work item, please subscribe and add any appropriate comments. Cheers, Geoff manoj.panda wrote: In Scrum process: The Release has been divided to several Sprint. If |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.