Burndown chart on a single epic

Hello,

We have a very big projet in RTC 2.0.0.2 in witch we have a lot of epics that have a user stories and task under them. We whant to follow each epic individually to have a vision on all part of the project.

Is there any way to do a report that can bring this info (maybe like a burndown or burnup) on epics in RTC ?

Thanks for you help!

0 votes



2 answers

Permanent link
To do this, we will need to collect all the children of the epic (recursively). Then we need to pass those to the Burdown/Burnup chart.

The above can be done with a new Report Template. But I am concerned about the performance of the report. Imagine if you have hundreds of child work items, the final SQL statement could have a huge IN clause and the database backend may not handle the final SQL efficiently.

So the answer to this, is currently, the RTC Data warehouse schema wont handle this report efficiently. Please raise a new feature request and we will consider for future releases.

0 votes


Permanent link

 "Please raise a new feature request and we will consider for future releases." From above answer by Rafik Jaouani - Is the feature ready? Can we use it in dashboard? 

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Apr 09 '10, 12:05 p.m.

Question was seen: 6,399 times

Last updated: Nov 29 '20, 11:43 p.m.

Confirmation Cancel Confirm