how to create a series of iterations in one operation

I want to create a series of iterations on a timeline, each the same
duration, running back-to-back, going from now to some future date.

e.g. iteration every two weeks from now till the end of the year.
Any simple way to do this?

--
John Kohl
Senior Software Engineer - Rational Software - IBM Software Group
Lexington, Massachusetts, USA
jtk@us.ibm.com
<http>

0 votes



2 answers

Permanent link
I want to create a series of iterations on a timeline, each the same
duration, running back-to-back, going from now to some future date.

Any simple way to do this?


Sorry, no. The UI only supports creating single iterations.

- Jared
Jazz Team Process

0 votes


Permanent link
I've submitted work item 105047 for this request.

Cheers,
Geoff

jburns wrote:
jtk.us.ibm.comwrote:
I want to create a series of iterations on a timeline, each the same
duration, running back-to-back, going from now to some future date.

Any simple way to do this?

Sorry, no. The UI only supports creating single iterations.

- Jared
Jazz Team Process

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Feb 02 '10, 12:38 p.m.

Question was seen: 4,649 times

Last updated: Feb 02 '10, 12:38 p.m.

Confirmation Cancel Confirm