It's all about the answers!

Ask a question

Progress not shown


priya benjamin (111) | asked Feb 01 '10, 5:54 p.m.
we are new to RTC and we have a project, sprints setup etc..

The problem is even though developers are closing their work items, the progress bar keeps showing 0 items complete. Any ideas why?

8 answers



permanent link
Johannes Rieken (1.2k1) | answered Feb 02 '10, 8:53 a.m.
On 2/2/10 12:07 AM, pbenja1 wrote:
we are new to RTC and we have a project, sprints setup etc..

The problem is even though developers are closing their work items,
the progress bar keeps showing 0 items complete. Any ideas why?


Can it be that you are looking at a progress bar that renders its
progress based on story points and your developers report their progress
in hours?

--
Cheers, Johannes
Agile Planning Team

permanent link
priya benjamin (111) | answered Feb 02 '10, 11:25 a.m.
Thanks Johannes

That may be the case, do you know how could we switch the progress bar to show hours as opposed to storypoint?

permanent link
priya benjamin (111) | answered Feb 02 '10, 11:41 a.m.
Just asked the team and they said the progress bar shows hours with 0 progress even though they are closing items. So do you have any other suggessions?

permanent link
Michael Schneider (886) | answered Feb 09 '10, 4:53 a.m.
JAZZ DEVELOPER
On 2/2/2010 5:53 PM, pbenja1 wrote:
Just asked the team and they said the progress bar shows hours with 0
progress even though they are closing items. So do you have any other
suggessions?



the work items which your developers close are most probably of a type
marked as "top level type". For top level work items, the complexity is
used to calculate the progress, the estimates are ignored, even if they
are specified.

--
MikeS
Agile Planning Team

permanent link
Vincent Huynh (14697) | answered Feb 09 '10, 11:10 a.m.
Hi Michael,

I have a similar problem with the progress bar roll up:

The progress bar in the 'Story' work item, and the progress bar when I have a View As 'Grouping' (Folder, Category, etc.) do not reflect progress as I had imaged.

I have a task with Estimate 100h, and Time Remaining 40h (In Progress state). The progress bar shows: "0/40h", and does not seem to progress if I modify the Time Remaining field the next day...

Can you tell me why it is doing this and not "60h/100h" for instance...

Thanks in advance,
Vince-

permanent link
Vincent Huynh (14697) | answered Feb 09 '10, 12:00 p.m.
Hi Michael,

I have a similar problem with the progress bar roll up:

The progress bar in the 'Story' work item, and the progress bar when I have a View As 'Grouping' (Folder, Category, etc.) do not reflect progress as I had imaged.

I have a task with Estimate 100h, and Time Remaining 40h (In Progress state). The progress bar shows: "0/40h", and does not seem to progress if I modify the Time Remaining field the next day...

Can you tell me why it is doing this and not "60h/100h" for instance...

Thanks in advance,
Vince-


"Task" work item was marked as a Top-Level Work Item. Removing it fixes the problem... thanks! :)

Vince-

permanent link
Anthony Kesterton (7.5k9180136) | answered Feb 10 '10, 6:13 a.m.
JAZZ DEVELOPER
Hi Michael,

I have a similar problem with the progress bar roll up:

The progress bar in the 'Story' work item, and the progress bar when I have a View As 'Grouping' (Folder, Category, etc.) do not reflect progress as I had imaged.

I have a task with Estimate 100h, and Time Remaining 40h (In Progress state). The progress bar shows: "0/40h", and does not seem to progress if I modify the Time Remaining field the next day...

Can you tell me why it is doing this and not "60h/100h" for instance...

Thanks in advance,
Vince-


I believe that progress will be measured in the progress bar against a completed task. not your estimate of progress on an individual task. If you complete a task - does that make a difference?

anthony

permanent link
Vincent Huynh (14697) | answered Feb 10 '10, 12:14 p.m.
Hi Michael,

I have a similar problem with the progress bar roll up:

The progress bar in the 'Story' work item, and the progress bar when I have a View As 'Grouping' (Folder, Category, etc.) do not reflect progress as I had imaged.

I have a task with Estimate 100h, and Time Remaining 40h (In Progress state). The progress bar shows: "0/40h", and does not seem to progress if I modify the Time Remaining field the next day...

Can you tell me why it is doing this and not "60h/100h" for instance...

Thanks in advance,
Vince-


I believe that progress will be measured in the progress bar against a completed task. not your estimate of progress on an individual task. If you complete a task - does that make a difference?

anthony

When I marked it Complete, the progress would become "0h/0h". Now that Tasks are not a Top-Level WI, it works as it should.