Progress not shown
we are new to RTC and we have a project, sprints setup etc..
The problem is even though developers are closing their work items, the progress bar keeps showing 0 items complete. Any ideas why? |
8 answers
On 2/2/10 12:07 AM, pbenja1 wrote:
we are new to RTC and we have a project, sprints setup etc.. Can it be that you are looking at a progress bar that renders its progress based on story points and your developers report their progress in hours? -- Cheers, Johannes Agile Planning Team |
Thanks Johannes
That may be the case, do you know how could we switch the progress bar to show hours as opposed to storypoint? |
Just asked the team and they said the progress bar shows hours with 0 progress even though they are closing items. So do you have any other suggessions?
|
On 2/2/2010 5:53 PM, pbenja1 wrote:
Just asked the team and they said the progress bar shows hours with 0 the work items which your developers close are most probably of a type marked as "top level type". For top level work items, the complexity is used to calculate the progress, the estimates are ignored, even if they are specified. -- MikeS Agile Planning Team |
Hi Michael,
I have a similar problem with the progress bar roll up: The progress bar in the 'Story' work item, and the progress bar when I have a View As 'Grouping' (Folder, Category, etc.) do not reflect progress as I had imaged. I have a task with Estimate 100h, and Time Remaining 40h (In Progress state). The progress bar shows: "0/40h", and does not seem to progress if I modify the Time Remaining field the next day... Can you tell me why it is doing this and not "60h/100h" for instance... Thanks in advance, Vince- |
Hi Michael, "Task" work item was marked as a Top-Level Work Item. Removing it fixes the problem... thanks! :) Vince- |
Hi Michael, I believe that progress will be measured in the progress bar against a completed task. not your estimate of progress on an individual task. If you complete a task - does that make a difference? anthony |
Hi Michael, I believe that progress will be measured in the progress bar against a completed task. not your estimate of progress on an individual task. If you complete a task - does that make a difference? anthony When I marked it Complete, the progress would become "0h/0h". Now that Tasks are not a Top-Level WI, it works as it should. |