JRS - Report Builder - Different results for LQE and DW
7.0.2-ifix28
In ETM, I browse all test plans = 18
In LQE, I connect to ETM Project, select Test Plan and just click Run Report = 18
In DW, I connect to ETM Project, select Test Plan and just click Run Report = 15.
Any troubleshooting tips?
|
One answer
Hi Sterling -
How often is your data warehouse refreshing? Since LQE is "near real time" I would expect it to be closer to up to date with ETM. There's usually a lag between the updates in the product and when the data warehouse has updated.
Comments
Sterling Ferguson-II
commented Jul 31, 10:45 a.m.
Hello,
It's about every 4 hours, and there was a reindex last night for troubleshooting (LQE used to be 15 as well). So this is going on about 2-3 days since we first noticed.
|