Why Proposed type of snapshot "Proposed Start Date = Date when snapshot is taken"

I have a project area with Formal Project Management Process template. When I created the snapshot following unexpected behaviours are noticed: 


  • I have a plan with existing workitem (task). 
  • For a task which is supposed begun in the past (As per planned start date), I have changed the effective estimate and took snapshot with type "proposed". 
  • Why is proposed snapshot changes the proposed start date to today's date (Date of taking snapshot). 

How do I prevent this ?

0 votes


Accepted answer

Permanent link

Actual purpose of "proposed start date" is to track the extended estimate of a workitem after changing/extending the effective estimate.

If we want to find the actual start date of the workitem we will need to refer to "planned start date" field.
Hence, we can say this is the expected behaviour to change the Proposed Start Date to Date on which the proposed snapshot is taken.



Ralph Schoon selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: Apr 20 '24, 1:50 p.m.

Question was seen: 486 times

Last updated: Apr 20 '24, 2:05 p.m.

Confirmation Cancel Confirm