Work Hours Done in RTC Plan (Progress Report) considers Cancelled Task
In RTC Plan there is a mismatch between the hours in "Time Spent" of each tasks and hours in "Progress Report" -> Work Hours Done.
"Work Hours Done" considers the "Estimate" or "Corrected Estimate" of Cancelled Tasks if the "Time Spent" is blank.
For Ex: Work Hours Done = 62.5 hours
Time Spent of all Tasks = 60.5 hours
Corrected Estimate of Cancelled Task = 2 hours
Cancelled with no Time Spent should not be considered for total Work hours Done
Request to clarify on why tool considers the Estimate of Cancelled Tasks
2 answers
If you think there is a defect, please open a case with support. Maybe someone else knows the details of the reports and the planning. I do not.
My assumption would be, if the Estimate and the time spent or time remaining show work being done, then this should be counted regardless if the work item got canceled. The work was done and does not go away, just because the work item is canceled.