Hello everyone,
is there a way to use two risk matrices when you have two different impacts and probabilities? It seems like this is not possible since com.ibm.team.tpt.presentation.risk.matrix uses com.ibm.team.workitem.workItemType.risk.impact and com.ibm.team.workitem.workItemType.risk.probability and you can not create more than one attribute with the same ID.
Has maybe anyone found a way to solve this issue?
Thanks in advance |
Accepted answer
Ralph Schoon (63.4k●3●36●46)
| answered Jun 12 '23, 4:23 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER As far as I can tell, the Risk Matrix is a Non-Attribute-based Editor Presentation. I can not see any ways of being able to configure the attribute ID's that it uses to get the values to calculate the risk matrix. I have to assume that the ID's are hard coded in the presentation code. So, for all I can see, if you add the risk matrix multiple times, it will always show the same data. K. Hartig selected this answer as the correct answer
|
One other answer
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.