It's all about the answers!

Ask a question

More than one Risk Matrix in Risk Work Item


K. Hartig (132) | asked Jun 09 '23, 8:04 a.m.
Hello everyone,

is there a way to use two risk matrices when you have two different impacts and probabilities? It seems like this is not possible since com.ibm.team.tpt.presentation.risk.matrix uses com.ibm.team.workitem.workItemType.risk.impact and com.ibm.team.workitem.workItemType.risk.probability and you can not create more than one attribute with the same ID.
Has maybe anyone found a way to solve this issue?

Thanks in advance

Accepted answer


permanent link
Ralph Schoon (63.4k33646) | answered Jun 12 '23, 4:23 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 As far as I can tell, the Risk Matrix is a Non-Attribute-based Editor Presentation. I can not see any ways of being able to configure the attribute ID's that it uses to get the values to calculate the risk matrix. I have to assume that the ID's are hard coded in the presentation code. So, for all I can see, if you add the risk matrix multiple times, it will always show the same data.

K. Hartig selected this answer as the correct answer

One other answer



permanent link
K. Hartig (132) | answered Jun 18 '23, 2:43 a.m.
Thanks a lot.

Your answer


Register or to post your answer.