More than one Risk Matrix in Risk Work Item
Hello everyone,
is there a way to use two risk matrices when you have two different impacts and probabilities? It seems like this is not possible since com.ibm.team.tpt.presentation.risk.matrix uses com.ibm.team.workitem.workItemType.risk.impact and com.ibm.team.workitem.workItemType.risk.probability and you can not create more than one attribute with the same ID.
Has maybe anyone found a way to solve this issue?
Thanks in advance
Accepted answer
As far as I can tell, the Risk Matrix is a Non-Attribute-based Editor Presentation. I can not see any ways of being able to configure the attribute ID's that it uses to get the values to calculate the risk matrix. I have to assume that the ID's are hard coded in the presentation code. So, for all I can see, if you add the risk matrix multiple times, it will always show the same data.