Alan Murphy (531414) | asked Dec 11 '09, 8:06 a.m.
We have an exisiting project which we created a process template from. We then used that template to create a new project, but when we try and initiliase it we get this error

Problem
An unhandled exception occurred during "Setup Project".

CRJAZ0215I Item not found: com.ibm.team.workitem.common.internal.model.impl.CategoryHandleImpl@67326732 (stateId: , itemId: , origin: <unset>, immutable: <unset>)

Reason
Initializes a project area with the pieces necessary to start work on a project.


So clearly something is missing, but what ????

Any suggestions appreciated

3 answers



permanent link
Marcel Bihr, Jazz Work Item team (1.4k) | answered Dec 11 '09, 8:39 a.m.
JAZZ DEVELOPER
Hi
It seems that a category is missing or referenced from an unexpected point. Could you please file a defect work item against the work items component and attach your process template source.

Regards

Marcel
Work Item team

permanent link
Ulf Buchner (3182213) | answered May 10 '10, 8:32 a.m.
Hi Marcel,

I have a similar problem at a customer's site. Is this a bug or a configuration problem? We're running RTC 2.0 on IBM i.

See the error below:

Problem
An unhandled exception occurred during "Setup Project".

CRJAZ0215I Item not found: com.ibm.team.workitem.common.internal.model.impl.CategoryHandleImpl@59225922 (stateId: , itemId: , origin: <unset>, immutable: <unset>)

Reason
Initializes a project area with the pieces necessary to start work on a project.


Thanks,

Ulf
Synobsys Netherlands

permanent link
Ulf Buchner (3182213) | answered May 10 '10, 10:46 a.m.
Hi
It seems that a category is missing or referenced from an unexpected point. Could you please file a defect work item against the work items component and attach your process template source.

Regards

Marcel
Work Item team


Problem solved. I removed the Work item type "task" for my template, but this is used when the initial work items are created. So removing the initial work item creation part solved it.

Thanks,

Ulf