How are "Problems detected" calculated on Plans?
We are using RTC 2.0.0.1 for this project. While looking at the current iteration in the plan editor, it is reporting "Problems detected". The iteration is set to end on 12/10. The work items in the pop-up for the problems are listed as: The work item is planned to be completed on Dec 11, 2009, while the iteration ends on Dec 10, 2009." Looking at the work item, I see no field that indicated it is planned to be completed on 12/11... how is RTC calculating that? How do we fix the "problem"?
Thanks for the help,
Julie
Thanks for the help,
Julie
One answer
jmrotter wrote:
The planned completion date is computed based on the sequence of work
items, their estimates, and the available time of their owner.
For instance, a contributor works 8hrs a day, has three 8hr work items
left, but the iteration ends in 2 days. In such a case above warning is
emitted.
--
Cheers, Johannes
Agile Planning Team
We are using RTC 2.0.0.1 for this project. While looking at the
current iteration in the plan editor, it is reporting "Problems
detected". The iteration is set to end on 12/10. The work
items in the pop-up for the problems are listed as: The work item is
planned to be completed on Dec 11, 2009, while the iteration ends on
Dec 10, 2009." Looking at the work item, I see no field that
indicated it is planned to be completed on 12/11... how is RTC
calculating that? How do we fix the "problem"?
The planned completion date is computed based on the sequence of work
items, their estimates, and the available time of their owner.
For instance, a contributor works 8hrs a day, has three 8hr work items
left, but the iteration ends in 2 days. In such a case above warning is
emitted.
--
Cheers, Johannes