Can we make delta change of presentation layer for a particular team area alone in EWM/RTC project area?
EWM 7.0.2
We are common project as template project area where all the required configurations area done.
We created another project area Project A inheriting the template from common project and have multiple team areas underneath
Team A1
Team A2
Team A2
Now we need some delta change in presentation layer for Team A1 alone.
Team A2 should not see the attributes configured for Team A1.
Is there a way to do the above delta changes?
One answer
No, the work item attribute configuration is shared across a project area. It is only possible to customize some few items on team area level e.g. permissions. When using the process of another project area, unless you break this usage, the work item attributes are set anyway, so the question does not make a lot of sense.
If you try to ask a different question, please exapand.