RTC 6.0.6.1 - Is there an easy way to change the 'type' of a work item from a plan view?


Glyn Costello (12920) | asked Jul 26 '22, 5:02 a.m.

...for several tasks in a large which have been created as "tasks" but need changing to other types.

One answer



permanent link
Ralph Schoon (62.3k33643) | answered Jul 26 '22, 8:36 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 A Plan view is not the right place for this. You can try to get the items with a work item query. Then you have bulk update capabilities to change the type of multiple items.