![]() Hi,
Can I use JRS to report on DNG artifacts only in a GCM environment. ETM and EWM are not GC configured. When in Report Builder I cannot see my DNG project which is under GC.
Thank you,
|
2 answers
![]()
David Honey (1.7k●1●7)
| answered Apr 22 '22, 4:44 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER edited Apr 22 '22, 4:45 a.m.
Just to clarify since the original question uses incorrect terminlogy. I've italicised the correct terminology for emphasis below.
If you have a GC hiearchy that includes contributions from DN local configurations, then you can report on the requirements in that global configuration. However, as Davyd Norris correctly points out, you can only do so using a Report Builder data source such as
Lifecycle Query Engine scoped to a configuration
.
If you want a report that includes traceability relationships between requirements and test artifacts from ETM, those test artifacts must be from ETM project areas that have also opted-in for configuration management. Comments Thanks Mr. Honey for you comments