Lifecycle Project with more than 1 RM Project Area
I have a DOORS RM project area RMProj01 and a change project area (EWM/RTC) CProj01
They are both in lifecycle project LCProj01 so I can link a change request in CProj01 to a Requirement in ReqProj01
If I have a second Reqs project area RMProj02 can I link a change request in CProj01 to a requirement in ReqProj02?
It seems I would need to add RMProj02 to lifecycle project LCProj01 before I could do this but that does not seem to be possible since it already has 1 RM project area.
Is there a maximum of 1 change project area and 1 RM project area in any given lifecycle project?
So do I need a separate change project area to manage changes for each Req project area?
Accepted answer
You can have multiple DOORS Next project areas in a lifecycle project. The default templates only create one, but you can add additional ones later. In the Lifecycle Project Administration page, just scroll down to the Additional Artifact Containers section, and click on "Add".
Comments
Yes, you have to add an association between any two project areas that want to link to each other. You would do that in the "Overview" section of the Project Area editor for the project.