Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

RTC planning forecast ability

 Hi, 

In case we have 2 developers, each one of them is working on his tasks. 
Developer A finishes his work quicker then Developer B. 

Does RTC uses this data in his planning? I mean, can RTC forecast that the feature is more likely to finish sooner because of good working skills some of the developers have? 
Or RTC just calculates the total hours within the iteration compare to the total estimated hours (& member's allocation)? 


Thanks, 

0 votes


Accepted answer

Permanent link
Hello, to my knowledge/understanding, RTC will use the available capacity of the developer and the remaining effort of a Task to calculate the forcase about the completion. thus, RTC will always assume a linear decrease of the remaining effort. Thus if a developer reduces the remaining effort (by updating the corresponding attribute) faster then this linear prediction the forecast for the completion date will as well be affected.
So RTC can of cause not consider the skill, but will dynamically adjust forecast calculations based on the remaining effort....



Bareket Matmon selected this answer as the correct answer

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: Dec 11 '19, 7:48 a.m.

Question was seen: 855 times

Last updated: Dec 11 '19, 8:03 a.m.

Confirmation Cancel Confirm