Execution schedule hangs with command line adapter
We're using RQM 6.0.6 and the command line adapter. Infrequently when we're running test schedules those will 'hang' at the end of the last test case in a suite. The process launched by the adapter has definitely completed and exited but the test suite execution record shows the final test as in progress. There's nothing in the adapter log to give any clue as to what has happened.
The adapter therefore never starts the tests in the next suite in the schedule.
Just wondered if anyone else is seeing this behaviour.
|
2 answers
Ralph Schoon (63.5k●3●36●46)
| answered Apr 18 '19, 3:47 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Paul, you might want to open a case with support. I have heard about a case similar to that in the past. |
Hi Paul,
We are also experiencing the same thing like yours and its actually difficult to monitor CLA window all the time.
May I know if you have already raised any ticket for same issue with IBM.
Please share if you have figure it out the issue.
Thanks.
|