RPE Report Cancelling Error Task "Rendering Report" cancelled exceeded configured maxium runtime


nannette Mori (50575) | asked Jan 22 '19, 9:27 a.m.

RPE Version 1.2.1

RTC 6.0.3

Created a RPE report to count how many times a DR failed in 2 states (Ready for Test, Ready For Verification).

Historically is used to take about 3 hours to run, but the report is no longer completing due to the following error:

Task "rendering Report" was cancelled: Task Running Time exceeded configured maximum Runtime. 

I kicked off this report yesterday at 2:30pm and it cancelled at 7:15am this morning. 

Is there a limit on the number of records RPE can report on? Currently we have 4983 DR records.  This report over time has steadily increased in how long the report has to run before it produces the data. 

Is there a setting that can configured to increase the maximum runtime?

The maximum Task report runtime is set to -1 so the report should never be automatically cancelled

Does anybody know how to keep the report from cancelling?

One answer



permanent link
Fariz Saracevic (904613) | answered Jan 22 '19, 11:07 a.m.
FORUM MODERATOR / JAZZ DEVELOPER

RPE does not have limit how many it can report on but I suggest that you upgrade to the latest version of RPE. RPE 1.2.1 is not supported since Sept. 30, 2017 (https://www-01.ibm.com/software/support/lifecycleapp/PLCDetail.wss?q45=Y931833L21023B77). You get performance improvements as well as the latest RPE features.