Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

RPE Report Cancelling Error Task "Rendering Report" cancelled exceeded configured maxium runtime

RPE Version 1.2.1

RTC 6.0.3

Created a RPE report to count how many times a DR failed in 2 states (Ready for Test, Ready For Verification).

Historically is used to take about 3 hours to run, but the report is no longer completing due to the following error:

Task "rendering Report" was cancelled: Task Running Time exceeded configured maximum Runtime. 

I kicked off this report yesterday at 2:30pm and it cancelled at 7:15am this morning. 

Is there a limit on the number of records RPE can report on? Currently we have 4983 DR records.  This report over time has steadily increased in how long the report has to run before it produces the data. 

Is there a setting that can configured to increase the maximum runtime?

The maximum Task report runtime is set to -1 so the report should never be automatically cancelled

Does anybody know how to keep the report from cancelling?

0 votes



One answer

Permanent link

RPE does not have limit how many it can report on but I suggest that you upgrade to the latest version of RPE. RPE 1.2.1 is not supported since Sept. 30, 2017 (https://www-01.ibm.com/software/support/lifecycleapp/PLCDetail.wss?q45=Y931833L21023B77). You get performance improvements as well as the latest RPE features.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 22 '19, 9:27 a.m.

Question was seen: 1,839 times

Last updated: Jan 22 '19, 11:07 a.m.

Confirmation Cancel Confirm