Burndown Charts for RQM


Julian Hemm (54312) | asked Oct 04 '18, 8:06 a.m.
Hello,

I am looking for a way to visualize some kind of burndown / burnup chart for RQM.

It should show the time of the selected iteration on the x-axis and the TCERs (stacked planned/passed/failed) scheduled on this iteration on the y-axis.

Is there any possibility to do something similar?
So far I did not find any solution using the widgets or JRS.

Thanks in advance

One answer



permanent link
Jackie Albert (1.6k14846) | answered Oct 04 '18, 9:24 a.m.

 In Report Builder there is an 'Execution Trend' report under the ready-to-copy section.  Similarly, the out of the box RQM reports also have several variants of Execution Trend to take a look at.


Comments
Julian Hemm commented Jan 21 '19, 9:04 a.m.
Hello Jackie,

thank you for your response.
This does work for single test plans. Is there any possibility to report over a Master Testplan including all Child Testplans?

Jackie Albert commented Jan 21 '19, 9:36 a.m.

I'm honestly not sure, but I would guess no. Something I've been pushing for also is a way to do custom RQM reports via Report Builder similar to what you can do for RTC Work Items, but so far this capability is not available. I agree it would be nice.


Paul Slauenwhite commented Apr 04 '19, 7:09 a.m.