We are using RQM and have test cases and test suites. For weight, we have put everything down to 1 point. When we look at the Score Card:

Test Execution counts - Failed=17, Passed=20, Not Started=18
Test Result points - Failed=15, Passed=20, Not Started=32

What is the difference between the counts and points?

thanks

0 votes


Accepted answer

Permanent link
 Mahari,

The execution counts reflects the number of time execution happened where as points are the one you specify during the test planning to conclude sizing of it.

Regards,
Mehul

Mahari Hill selected this answer as the correct answer

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,021
× 7,495
× 481

Question asked: Aug 27 '15, 11:46 a.m.

Question was seen: 3,410 times

Last updated: Sep 03 '15, 9:41 a.m.

Confirmation Cancel Confirm