Unable to see any progress in a Plan View
I'm setting up a new project area with a new iteration plan.
I have created a project area iteration plan with work items in it. I have filled in the Estimate and Time Spent fields for the work items.
However the progress indicators on the plan show empty. I see the note "Progress: 0/82h Estimated 100%" underneath a white bar.
I went in and changed some of the work items to closed state. I'd like to know how to see the red/green progress bar with some hours showing as complete but I still see the same empty progress indicator.
What do I need to do to see progress greater than 0?
I have created a project area iteration plan with work items in it. I have filled in the Estimate and Time Spent fields for the work items.
However the progress indicators on the plan show empty. I see the note "Progress: 0/82h Estimated 100%" underneath a white bar.
I went in and changed some of the work items to closed state. I'd like to know how to see the red/green progress bar with some hours showing as complete but I still see the same empty progress indicator.
What do I need to do to see progress greater than 0?
2 answers
gastonw wrote:
I might be that all work item types are marked as top-level types. Goto
the project area editor, select the Process Configuration tab and expand
the node Project Configuration > Configuration Data > Planning >
Top-Level Work Item Types. Hourly progress is reported on *none* top
level work item types only.
--
Cheers, Johannes
Agile Planning Team
I'm setting up a new project area with a new iteration plan.
I have created a project area iteration plan with work items in it. I
have filled in the Estimate and Time Spent fields for the work items.
However the progress indicators on the plan show empty. I see the
note "Progress: 0/82h Estimated 100%" underneath a white
bar.
I went in and changed some of the work items to closed state. I'd like
to know how to see the red/green progress bar with some hours showing
as complete but I still see the same empty progress indicator.
What do I need to do to see progress greater than 0?
I might be that all work item types are marked as top-level types. Goto
the project area editor, select the Process Configuration tab and expand
the node Project Configuration > Configuration Data > Planning >
Top-Level Work Item Types. Hourly progress is reported on *none* top
level work item types only.
--
Cheers, Johannes
Agile Planning Team
gastonw wrote:
...
I might be that all work item types are marked as top-level types. Goto
the project area editor, select the Process Configuration tab and expand
the node Project Configuration > Configuration Data > Planning >
Top-Level Work Item Types. Hourly progress is reported on *none* top
level work item types only.
--
Cheers, Johannes
Agile Planning Team
Thanks, Johannes, that did the trick!