Is it possible to lock a DNG change set from further changes in order to assure that all reviewers are reviewing the same changes? (i.e. that additional changes are not made in the change set after one or more approvers have given their approval in RTC).


Comments
Geoffrey Clemm commented Feb 05 '19, 4:19 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

This is supported in RTC, but I couldn't find a way in DNG 6.0.6 ... has anyone else found a way? 

One answer



permanent link
Bas Bekker (1.4k4) | answered Feb 05 '19, 11:57 p.m.
JAZZ DEVELOPER
Looks like the same question discussed in this post: DNG 6.0.3: is it possible to "complete" a change set (before delivery)?
The question does not cover the review part, but the answers do.

Hope that helps.