how to configure Backlog Iteration on a shared process Project Area ?


Cesar Sasaki (511285126) | asked Apr 12 '18, 1:38 a.m.
edited Apr 12 '18, 2:37 a.m.

Hi I have created a project area that uses the process configuration from another project area.
I can create new timelines on the new "child" project area but I cant set up the backlog iteration because that is set up on the "Master Project Area".

Is there anyway?

One answer



permanent link
Ralph Schoon (63.1k33646) | answered Apr 12 '18, 9:07 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

What if you remove the backlog iteration in the sharing process?


Comments
Cesar Sasaki commented Apr 12 '18, 10:51 a.m. | edited Apr 12 '18, 11:08 a.m.

Hi Ralph

I'm  using a backlog iteration on the "Master" Project Area already.  And I have workitems planned for that iteration.


Ralph Schoon commented Apr 12 '18, 10:55 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

My understanding has always been that the whole purpose of the master project is to be a process provider. It is not supposed to be used. My experience has been that If you have a real working project then you can't even share its process any more.