As the members are shared across the teams and projects, is it possible to query to find details of all members of a particular team/project area

(1) The member's availability in terms of scheduled leaves
(2) percentage allocation made available for the project

Today the only option is to open each user profile and then see the percentage marked and then check the leave's planned


This will help a lot in allocating the work initially.

Thx & Regards
Jagadish

2 answers



permanent link
Johannes Rieken (1.2k1) | answered Sep 30 '09, 2:56 a.m.
jramakri wrote:
Hi

As the members are shared across the teams and projects, is it
possible to query to find details of all members of a particular
team/project area

(1) The member's availability in terms of scheduled leaves
(2) percentage allocation made available for the project

Today the only option is to open each user profile and then see the
percentage marked and then check the leave's planned


This will help a lot in allocating the work initially.


That's currently not supported. Some data is included in reports, but
there is no query functionality. Pls file an enhancement request to
bring this on our radar.

--
Cheers, Johannes
Agile Planning Team

permanent link
Jagadish R Rao (10612111) | answered Oct 05 '09, 8:58 a.m.
Hi

I have raised an enhancement request to capture the same
https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=95943&tab=overview

Thx & regds
Jagadish

jramakri wrote:
Hi

As the members are shared across the teams and projects, is it
possible to query to find details of all members of a particular
team/project area

(1) The member's availability in terms of scheduled leaves
(2) percentage allocation made available for the project

Today the only option is to open each user profile and then see the
percentage marked and then check the leave's planned


This will help a lot in allocating the work initially.


That's currently not supported. Some data is included in reports, but
there is no query functionality. Pls file an enhancement request to
bring this on our radar.

--
Cheers, Johannes